WIRING DUAL AMP VOLT METERS

After getting back to work from the Holiday, my work load was light and the weather outside was great, so ended up taking a day and a half off to work on the Fiero.

By Wednesday evening one of the duel meters was working, so I did a short video.


PACK DUEL METER WORKING 

Later on Wednesday evening, I started putting the LED lights in the instrument panel. The lowest wattage bulbs were not bright enough, so had to go with higher wattage LED bulbs. Then I blew a fuse while trying to get one of the bulbs in, so will need to go get some fuses.

Thursday morning I called Hebron Scrap and confirmed that they were open. The said they were, so the car was loaded up and off I went to unload some junk. Surprisingly, I got $63.00 for the pile that had accumulated in the Better Place shipping crate, so I put it in my fund to buy new leather seat covers.

Then a shunt was placed on the negative side of the 12 volt battery and connections were made to the lower duel meter in the instrument pane. While trying to remove the drivers side, front blinker light socket, my arm touched the battery pack and chassis ground, giving me a little jolt. Great! All I need is a battery leak to ground. When I was hooking up the low voltage duel meters, I hooked the red wire to 12 volt positive. This was a mistake because actually the red wire hooked to the pack 120 positive side of the shunt, and I fear with the ground leak, blew the high voltage meter 12 volt power supply. Anyway, only the lower meter is working now, so I ordered another meter from EBAY. When the proper wires were hooked up on the 12 volt meter, It read 13.8 volts but I could not get a current reading. Not sure if power is feeding through the dc-dc converter ground and not actually going from the battery, but I will need to do a little more work to try and get a reading of some kind from the 100 amp shunt on the 12 volt system. 

Hopefully I can get the meter that is probably blown out of the instrument pod by removing the face, as I am not thrilled about the possibility of taking the instrument pod out again.

The right angle micro a/b USB arrived today, so I will also need to work on getting the USB wire run to power up the Dell Venue 8 Pro.


MICRO A/B RIGHT ANGLE USB CABLE

A refurbished Powerlab 6 was ordered and should be here in a couple of days to do the second bottom balance of the Better Place module. All of the cells have been brought down below 2.8 volts but have drifted back to 2.85 or so. The Powerlab 6 will allow me to set a much tighter voltage range and I can let it set and cycle at a low amperage drain to try an being them all in line. I have a multi cell cable but am not sure if that will allow me to bottom balance 6 at a time, so will need to play with the Cellpro for awhile to see if that will work. If any of you have used a Cellpro with the multi cell connector to bottom balance, shoot me an email at randy@cz-ev.com

Thanks for stopping by,

Randy 

Monday, October 7, 2013

CONNECTING THE CONTROLLER



The Synkromotive controller comes with a pre-wired unterminated assembly that plugs into a 23 position AMPSEAL Connector on the side of the case. It looks like spaghetti and has wires for forward and reversing contactors that are not needed in my build. I considered removing the unused wires but was afraid I would break the connector, so will just hide them in split loom. The placement of wires in the connector do not group the wires going to different components very well causing them to tangle but I believe I finally got all of them straightened out pretty well. 



CONTROLLER WIRING


AMPSEAL CONNECTOR

Hopefully, next weekend I will be able to install the main battery connectors and charge the pack. I have also been working on contactor and fuse placement and am looking for a place to put the shunt, so I can measure pack current. I don't want to cut the battery cables in the engine compartment as battery packs will eventually be installed there and I don't want to have to splice them, so may leave them a little long for now. With the transaxle and motor cradle installed, it is a bit awkward getting to the motor compartment wiring.

Reading the controller manual and prearranging the wires has slowed me down quite a bit but I hope to pick up the pace in the coming weeks.

Until next week,

Randy

Tuesday, September 10, 2013

NATIONAL PLUG IN DAY COLUMBUS, OH

I just ran across the Plug In America National Plug in day and found there is going to be an event in Columbus, OH; so I registered. . There are at least 7 EV builders in Central Ohio, who are in different stages of conversions, from getting components together,  to having fully operational EVs. This may be a good place for everyone to get together and possibly meet some new folks interested in electric transportation.




Event: Columbus, OH
Day: Saturday, September 28th, 2013
Time: 1-4 PM
Location: Columbus College of Art and Design Parking Lot (MAP)
               44 Cleveland Ave
               Columbus, OH, United States


Hope to see you there.

Randy

Saturday, September 7, 2013

LABORING ON LABOR DAY

With the cradle back in the Fiero, Labor Day was spent installing the struts, brake lines, and parking brake cables. After cleaning the bolts and coating them with never seize, the struts were bolted up. I could see the marks where the bolts were riding originally and made sure to tighten them down in the same position, so my alignment should be pretty close to where it was..

Next the brake lines were installed but I wanted to use new bleeders and banjo bolt washers, so off to Advance Auto. I thought maybe they carried a vacuum pump brake line bleeder but said they did not carry anything like that. Advance is really high on bleeders & copper gaskets and I probably should have just gone to NAPA to get them. The brake line goes up across the top of the rear engine compartment and with the car jacked up, am afraid that is where all of the air is going to collect. I thought if I could pull a vacuum and get a little brake fluid flow going, maybe it would pull the air out the drivers side bleeder, that is the furthest away from the master cylinder. I pumped the brakes all day but still do not have any pedal. I did use the power brake vacuum pump to get the fluid to start moving but had it hooked up directly to the bleeder, so once the fluid filled the tube, it started going into the pump. I plugged the IOTA DC-DC converter into AC and used the 12 volt battery to run the pump. This also gave me a chance to monitor the voltage which seemed to go as low as 12 volts and as high as 13.9 volts.


MONITORING BATTERY

Also I hooked up the parking brake cables and had to spend quite a bit of time getting the adjusting screw freed up, so the final adjustment could be made. I spent a little time on the internet reading a couple articles on how to adjust the parking brake, as I have been told it can be a little tricky to get it working correctly.

 Tuesday I took a half day off work and continued to work on bleeding the brakes. The new bleeder valves did not seem to tighten correctly and I ended up twisting one off. They had Teflon tape on the threads and you could not feel when they seated. After drilling out the broken bleeder I tapped the threads back out with a 3/8 nc tap and just used the old bleeder valve, that was still like new.

I did not work on the car Wednesday night but went back out Thursday and was able to finally get the brakes to bleed. Then I started adjusting the parking brake. I got the leaver to tighten but will need to get the wheels back on the car and drive it in reverse a couple times to do the final adjustment, so on to hooking up the clutch slave cylinder. I painted the bracket and will put the wheels back on the car and lower it before installing the bracket, painting the slave cylinder, cleaning up the slave cylinder rubber and reinstalling it. The car shifted hard when I bought it but I moved the flywheel closer to the transaxle which should give me a little more clutch travel. Hopefully I can get the shifter adjusted so it shifts better than it used to..



PARKING BRAKE ADJUSTER

Once the car is off the jack stands, I will be able to reach everything to finish the wiring. I am going to install all of the batteries in the front bay for now to get them all charged and find out if the charger can be adjusted down far enough without having to install the new chip. I am going to remove the charger from where it is mounted now and just use it from the bench to do the first charge on the batteries. Once everything is set up, I will install the rear battery boxes and mount the charger back in the rear of the car.  


FRONT BATTERY BAY
Every time I cycled the HiPower batteries, I seemed to get a little more capacity, so hopefully after the full pack is put together and cycled a couple of times, they will come a little closer to their 100 ah rating. My plan was to drive the car back and forth to work at AEP in Columbus, OH and with 40 100 AH batteries, may have been close to making the 44 mile round trip. With the batteries in their current condition, I may make it the 22 miles to work but will need to charge there to get back  home. A co-worker with a Volt was finally able to get a parking place with a charger for $10 extra/month, so that would be a pretty good deal if there are any more spaces available.

I took another 1/2 day off Friday and cleaned up and put away tools. After getting the garage back in order, the rear wheels were mounted and the car lowered off of the jack stands. I cleaned up the front bay and did some measuring to make sure the 38 batteries would all fit in the front, and they will.  


Work continues on hooking up the clutch slave cylinder and shifter cable brackets and by the end of the weekend, should have them mounted.


CLUTCH SLAVE CYLINDER




THROW OUT BEARING LEAVER

I still have the remainder of the weekend to get some more work done but am going to go ahead and post, since I started writing it on Memorial Day. The car is getting closer to testing but I still do not have battery connectors from CALB yet. To help keep the build under $10,000, I am going with the solid copper connectors but will use zinc terminal paste, Nord Lock Washers, and SS bolts. I have a company in China that says they can make the flat braided copper connectors but need to send them a detailed print before they will give me pricing.

Thanks for reading and hope to see you back for next week's post.

Randy

Sunday, September 1, 2013

ROCKING THE CRADLE

Over the last week I have been cleaning up under the car and preparing to lift the motor and transaxle cradle back into the Fiero. I purchased some solid cradle mounts from Rodney Dickman but when I tried to hammer out the old mounts, found that they were not going to just pop out.


SOLID ALUMINUM CRADLE BUSHINGS

I got on the internet and started looking for information on how to remove the front cradle bushings and on Pennock's Fiero Forum, found a post from a guy who had made a simple tool to remove them.


CRADLE BUSHING REMOVAL TOOL

I had a tail pipe adapter but did not have any all-thread that would work so stopped at Home Depot on my way home from work to pick up all-thread, washers & and nuts and Saturday morning I started the bushing removal. After applying  tension, a little heat was added to the center of the bushing bore with a propane torch and the bushing started sliding out. Ok, getting the bushing out was one thing but cleaning all of the rubber stuck to the inside of the bore was another! I had to heat and scrape, and heat and scrape, (of course being careful not to breath any of the smoke coming off of the burning rubber.) The solid bushing kit came with a flapper wheel to put on a drill, so after most of the rubber was scrapped off, was able to get it down to metal. The new aluminum bushing were machined perfectly and went right into the bore with a few light taps from a rubber mallet.

It was in the upper 80's with high humidity in Ohio on Saturday, so after getting the bushings installed in the cradle, went into the house to cool off and get a dry shirt. When I got on the computer to check  my email, my hands started cramping, I guess too much work in too much heat and not enough water caught up with me! After resting and watching a little of the Ohio State football, I went back out and started rigging up the jacks to lift the cradle. My wife wanted to go to the Millersport Sweet Corn Festival, so I wrapped up work on the car, got cleaned up, and we put the top down on the Miata. After walking around the festival for several hours, we had a very nice top down night ride through the country on the way home.


MILLERSPORT SWEET CORN FESTIVAL

Sunday morning, I slept a little later that normal and watched part of EVTV's Weekly Show before heading out to the garage.around 10:00. The transmission jack that I planned to use to lift the front of the cradle would not lift it, so I had to use a floor jack on the front of the cradle, the transmission jack on one rear corner, and a scissor jack on a dolly to support the other rear corner. It would have been nice to have had someone (my son) to operate the jacks while I was aligning the bushing holes but I was able to lift it into place and get it bolted up by myself. Having the cradle back in ROCKS!



MOTOR CRADLE INSTALLED

The cradle went in fairly easy but now the brake bleeding, adjusting the the parking brake, and getting the shifter linkage adjusted begins. I am going to put batteries in front of the motor and maybe a few to the rear of the motor so the motor and transaxle will be visible. During  the 24 hour film festival shoot last year, the movie crew wanted to see the car but all they could see were batteries and a table with the controller and a bunch of relays. When the Fiero is done, I want people to be able to see the electric motor.

Stop back,

Randy

Tuesday, August 27, 2013

READY TO INSTALL ENGINE CRADLE

This week I decided to test the charging relay and when I applied power, nothing happened. I checked the 12 volt battery and it was under 1 volt. After looking around the car I found the drivers side door was ajar and the interior lights had run the battery down. I hooked up the DC-DC converter to AC and let it charge until the voltage came up to 13.2 volts then disconnected the charger. When opening the drivers side door, the interior lights came on and the battery was still holding above 13 volts. It is good to know my bottom balance on the Ballistic battery worked and there did not appear to be any damage but may still install a timer circuit to take out the interior lights after a couple minutes, to prevent this from happening again. The battery is only 2.3 A/h but I only intended to have it power up the J1772 circuit and turn on the DC-DC converter when charging. I ran the lead acid batteries down a couple times when I forgot to unplug the DC-DC converter and wanted to have a way to shut it down when the ignition switch is turned to off.

The engine compartment is done and I am preparing to install the motor cradle. There will still be a few wires to run and some loom to install but I need to wait until the motor is in to decide on the routing.


MOTOR COMPARTMENT FINISHED

The controller will need to be removed from the motor to get clearance for the cradle to go back in and some wires will need to be tied up out of the way to keep from damaging them. The speedometer plug was pulled off when I dropped the cradle but thanks to EBAY, another one is on the way.


CONTROLLER MUST BE REMOVED

Only two batteries left to bottom balance and the pack will be ready for the initial charge. Out of the forty, four of them will not hold a charge, so that will leave me with 36 cells. None of them took more that 80 A/H and some of them only took 60 A/H. At 3.65 volts per cell, I will need to have the charger cut off at 130 volts or so but the charger is currently going to 156 volts and then doing a constant voltage stage. I changed the setting on the Zivan to "7", that is supposed to be for lithium but I will need to closely monitor the first charge.  There are a couple adjustments inside the charger for voltage and current so I am hoping the voltage can be turned down far enough using them. I have a chip for the Zivan that allows it to be programmed with a PIC3, so eventually, I want to install it so I will have a little better control of the charger. The Synkromotive Controller also has a charge function but there is no documentation on how to hook it up. There are settings in the set-up program but I am not sure anyone has tried to hook it up to AC using an inverter. If anyone has hooked the Synkromotive Controller up as a charger, leave a post and let me know how it worked out.

Thanks for viewing,

Randy


Monday, August 19, 2013

BACK IN THE SWING AFTER EVCCON

The battery bottom balancing continues and I am getting close to putting the motor cradle back in the Fiero. I
put together a Punch List of items to be completed while the cradle is still out of the car.

Punch List
  1. done   Connect ground to frame from 220 box 
  2. done   Straighten Negative battery lead 
  3. done   Mount 2 Rear relays 
  4. Redo driver side loom -  find and wire new speedometer connector
  5. Remount front to back battery cables
  6. done  Remove red wire from the tunnel (to heater contactor)
  7. done  Remove the black wire from the tunnel ( to vacuum pump motor)
  8. Remount heater wires
  9. Cover computer cavity
  10. done  Cut metal sticking out on front engine compartment firewall
  11. done    Rotate loom on fusible link wires 
  12. done    Tighten 220 plug nut 
  13. 13    Test relays
  14. 14    Touch up engine compartment paint 
  15. done    Change charge setting to lithium (position 7) on charger
The C500 switched 12 volts (2 wires), wire from the starter switch, and tachometer wires have been spliced into the connector and it has been installed. I used plenty of wire so I should not have to splice these wires when making the final connections.


WIRES SPLICED INTO C500 CONNECTOR

Two relays have been installed and the charger relay has 12 volts connected so when the charger turns on, the normally open relay closes and puts power on the relay and when the charger is off, the switched 12 volts will be applied to the relay through the charger's normally closed contact.


MAIN BATTERY CONTACTOR RELAY



I have been putting off sliding under the belly of the Fiero to re-mount the battery wires from the front to back packs and the heater power wires. They were bundled together along with the power wire for the vacuum pump and the heater relay wire. I am going to use a relay and get 12 volt power in the front of the car for the vacuum pump and use the starter wire to get power to the relay for the heater. That way I will be using original 12 volt wiring in the wiring harnesses for 12 volt control power and the only wires running on the outside of the car will be for the battery packs. I put loom on the 2/0 battery and heater power cables, where they made any bends or contacted any surfaces and used conduit hangers to mount the wires in the tunnel.


FRONT POWER CABLE MOUNTS


REAR POWER CABLE MOUNTS
There will either be an aluminum cover over the tunnel or a belly pan to cover the wires so they will not be exposed, after the car is running and I can get it on a lift.

Hopefully by September, I will have the motor cradle back in the car and can start on the battery boxes.

Monday, August 12, 2013

EVCCON III

This year's trip to EVCCON started out at 6 am EST from Ohio and I finally made the trip without getting side tracked, arriving at my Hotel in Cape Girardeau, MO around 3:00 PM CST. Around 5:30 PM CST I made my way over to the shop to pick up my credentials and the bag of goodies provided by EVTV.

Al Gajda was still tweaking in the new battery pack on his 39 Dodge pick-up conversion and did not have enough time to bottom balance before the convention started, so was carefully monitoring after each drive. The open source crew was working to get the DEMOC 645 to drive the Siemens motor on the VW Thing, and Brandon Hollenger was completing wiring on the London Taxi, the winner of the EVCCON I, Build Your Dream  EV Contest.

As in the past, EVTV had a very nice welcoming reception with good food and an open bar for the attendees. There were four of us from the Columbus, OH area and another from Akron, Ohio, so it was good to get together again. What is surprising is how many made the convention from other countries; New Zealand, Australia, and Great Britain to name a few. The attendance seemed down a little this year and it appeared there were fewer cars this year but still a strong showing.

It was surprising to not see NetGain Motors, Net Gain Controls, and Evnetics in attendance this year. HPEVS was the only manufacturer with a booth and EVTV was the only parts vendor. It was obvious there is somewhat of a shift to AC motors in the future of EV builds and with HPEVS and Curtis Controls new product offerings would seem to be the Manufactures poised to benefit, at least in the short term. There is also talk of using an industrial controller to drive the HPEVS motors, as the Curtis Controllers are seriously limited with respect to the capability of the motor.  There also seemed to be some interest from the NEDRA drag racing group that was in attendance in the AC electric motors.

When I got to the shop there were so many builders to talk to, I just forgot to take any pictures but thanks to Jehu Garcia, I didn't have to. The link below is a recap of the first few days of EVCCON III.


 




 EVTV'S VW THING


CHARLIE AND TAMERA RICKMAN'S
1973 OPEL GT

  

 

 AL GAJDA'S 39 DODGE TRUCK



ILLUMINATI MOTORS SEVEN
 


HPEVS 200 CORVETTE

NAIL HANKE'S BRADLEY GT II
 


COBRA BUILD
 


JOHN METRIC'S MIATA
 


GARY BULMER'S BLAKELY BERNARDI
 

EV WEST'S BMW
 

I would have liked to put the $800 or so it costs to attend EVCCON and the week off work into the Fiero Build but felt the relationships developed at the convention will be more than worth the delay in the build.

Sunday, August 4, 2013

LAST POST BEFORE EVCCON

Tuesday around 4 am I am going to leave for EVCCON. That should get me to Cape Girardeau, MO
by 11 am central time when the shop opens. My Hotel room should be ready by early afternoon so I can check in and rest a little for the open house that evening. Al Gajda's 39 Dodge ev conversion was at the EVTV Shop over the weekend and you could see him installing the batteries on the EVTV WEBCAM . He must have got them in and the truck running because it is off of the lift and no where in sight now.

Getting the 12 volt power hooked up has been my main priority this week and I cleaned and installed the new C500 right half connector.



 

C500 RIGHT SIDE CONNECTOR

The battery was connected so I had my wife turn on the key so if there were any shorts, I could have her shut off the power and could quickly disconnect the battery if needed. She turned the key and nothing happened. I plugged in the IOTA DC-DC converter and the lights came on so I was a bit confused. From inside the engine compartment I could not see the top of the battery and when I stood up, found I had not hooked up the negative  battery  terminal and was out of crimp terminals, so finishing the 12 volt connections would have to wait until the next day. As there is no starter on an EV, I probably got a little carried away on the battery and battery charger cables, but I had them already and figured, they won't hurt anything.

The next morning I was off to ACE Hardware to pick up the crimp terminals and got the battery hooked up. The little Ballistic battery was able to power up the headlights and all of the 12 volt systems seemed to work just fine, so I went to the wires on the C500 connector and checked voltage on them.


LIGHTS POWERED UP


C500 CONNECTOR PIN OUT

Just as I suspected, pins B! & E3 were connected to the pink wire that had been spliced in the wiring harness and are 12 volts when the switch is turned to the run position.. Pin A4 is connected to the purple wire that was spliced in the wiring harness and is 12 volts when the switch is turned to the start position.

The basic 12 volt wiring is done and all that is left is to put loom on some of the wires going to the terminal block on the front firewall and to tidy up the main battery terminals. The ground terminal is an aluminum nut rivet and I picked up a stainless bolt and washer to connect the terminals to it. Also I put one of the solid trunk panels in that is from a 1884 Fiero, to see if it was going to provide enough protection from the elements for the DC-DC converter, battery and contactors; It appears it will.


COVER FROM TOP


COVER FROM BOTTOM

The wires coming in on the left harness go to the AVC2, the one on the right is the positive and the one on the left is the negative. The harness coming in from the bottom is coming from the Zivan Charger. The left wire coming out of the loom is the positive to the common terminal on the charger contacts, the one coming out of the loom on the third terminal from the left is the normally closed contact and the on furthest right goes to the normally open contact. The terminal above will go to the relay that controls the main battery contactors. The two wires on the top left are the positive and negative.


CHARGER CONTACT TERMINAL BLOCK


CHARGER CONTACT CONNECTIONS
   
The original build had a wire running under the car to power the brake vacuum pump so I will look for a switched 12 volt wire  in the front of the car to turn on the pump when the key is switched. on. There is also a wire to turn on the heater contactor running underneath the car that I will try to power form an existing harness wire. If I don't need the starter wire, I may run it to the heater switch under the dash and use it to operate the heater contactor.

The battery bottom balancing continues and I have about 25 to go. The capacity information will be good when I start putting the pack together as I may just leave out some of the lower capacity ones. Since I am bottom balancing, I think real low capacity cells will keep me from fully charging the good ones.

As I said last week, I will try to do a post or two from EVCCON and will post some links from some of the other converters who are posting from the show.

Thanks for  viewing,

Randy   
 

Saturday, June 16, 2012

POWER TO THE EV

Well, I finally got 220 hooked up to my garage, so I can finally charge up the batteries. Tomorrow I am going to the title office to transfer the title and get a 30 day tag.  Hopefully will be able to take the Fiero out for a drive. There are no gauges so it is going to probably be an adventure until I figure out how far the car will go with 2 year old lead acid batteries.